Home / News / WASAP — Terms of Reference: Consultancy Services for Feasibility Studies, Detailed Engineering Design, Procurement Support, Construction Supervision and Defects Liability Support

WASAP — Terms of Reference: Consultancy Services for Feasibility Studies, Detailed Engineering Design, Procurement Support, Construction Supervision and Defects Liability Support

September 14, 2026 Investor Relations, latest_news, Press Releases, Public Notice
WASAP — Terms of Reference: Consultancy Services for Feasibility Studies, Detailed Engineering Design, Procurement Support, Construction Supervision and Defects Liability Support
Terms of Reference — Consultancy Services for Feasibility Studies, Detailed Engineering Design, Procurement Support, Construction Supervision and Defects Liability Support | NAWEC
NAWEC Logo

Mamady Maniyang Highway, Kanifing  ·  P.O. Box 609, Banjul, The Gambia  ·  Tel: (+220) 5289009  ·  info@nawec.gm

Project ID: P513113
Republic of The Gambia · Ministry of Petroleum, Energy and Mines · NAWEC / WASAP Project Implementation Unit
World Bank / IDA P513113
📄 Terms of Reference  ·  WASAP — Gambia Water and Sanitation Project

Consultancy Services for Feasibility Studies, Detailed Engineering Design, Procurement Support, Construction Supervision and Defects Liability Support

Urban Water Supply Systems in Kombo East and Urban Sanitation Infrastructure in Kotu and Banjul
Project: WASAP — P513113
Selection: Quality and Cost Based (QCBS)
Duration: 46.5 months
Contract Type: Lump-sum / Time-based
Financing: World Bank / IDA
📋
Approved Terms of Reference — Full Document (PDF) WASAP P513113  ·  Consultancy Services for Feasibility Studies, Engineering Design, Procurement Support, Construction Supervision and Defects Liability Support  ·  Official Use Only
⬇ Download TOR (PDF)
🌍

World Bank Financed Assignment — Official Use Only

This Terms of Reference is issued under the Gambia Water and Sanitation Project (WASAP — P513113), financed by the World Bank/IDA. The assignment shall comply with the World Bank Environmental and Social Framework, applicable Procurement Regulations for IPF Borrowers, and all applicable laws and standards of The Gambia. Selection is by Quality and Cost Based Selection (QCBS).

Background & Context

The Greater Banjul Area is The Gambia’s principal urban and economic centre. Urban water services face production constraints, intermittent supply, low pressure, aging infrastructure, limited storage, and high non-revenue water. Sanitation services in Banjul and Kotu are constrained by deteriorated sewerage assets, underperforming treatment systems, and inadequate fecal sludge management.

WASAP is the first standalone Water Supply and Sanitation Project in The Gambia with Performance-Based Conditions in the sector. The project will finance priority infrastructure to reduce service gaps in the Greater Banjul Area — including new boreholes, treatment and storage facilities, expansion of distribution networks, household connections, and measures to reduce non-revenue water. It will also strengthen sanitation service delivery through investments in a fecal sludge treatment plant and flood-resilient sanitation systems.

The assignment will prepare and supervise investments in two closely linked components: urban water supply in Kombo East/Brikama East, and urban sanitation in Kotu and Banjul.

46.5 Months
Assignment Duration
Overlapping phases as approved
5 Phases
Scope Structure
Feasibility through Defects Liability
~50 km
Distribution Network
~6,000 new household connections
19 Experts
Key Personnel
Indicative key expert positions

Investment Components

Component Core Investment Scope
Urban Water Supply Brikama East water treatment facilities; four boreholes; raw-water and treated-water mains; ground and elevated storage; clear-water pumping; medium-voltage power and backup supply; SCADA; approximately 50 km of distribution network; and approximately 6,000 new household connections.
Urban Sanitation Kotu fecal sludge treatment plant; Kotu wastewater treatment plant rehabilitation/expansion; priority sewer rehabilitation in Kotu and Banjul; Banjul sea outfall condition assessment and works as justified; and maintenance equipment.

Assignment Objectives

Overall Objective

To prepare technically sound, climate-resilient, environmentally and socially compliant, economically justified, and procurement-ready urban water and sanitation investments — and to support their implementation through procurement, construction supervision, commissioning, and the defects liability period.

Specific Objectives
  • Validate demand, service areas, beneficiaries, design criteria, and priority investment needs
  • Assess existing systems and identify least-cost, lifecycle-efficient solutions
  • Prepare feasibility studies, detailed designs, BOQs, and complete procurement packages
  • Integrate climate resilience, energy efficiency, environmental and social requirements
  • Provide technical support throughout bidding and contract award
  • Administer and supervise works through testing, commissioning, handover, and defects correction
  • Build NAWEC capacity through structured training and O&M documentation

Five-Phase Scope of Work

1
Feasibility Study
Approved preferred investment options, safeguards, costs, risks and implementation plan
2
Detailed Engineering Design
Procurement-ready designs, specs, drawings, BOQs, cost estimates and O&M provisions
3
Procurement Support
Technically responsive bidding process and completed technical evaluation support
4
Construction Supervision
Works completed per contracts, designs, quality standards, E&S requirements and schedules
5
Defects Liability Support
Defects identified, corrected, verified and closed before final completion

Firm Qualifications & Experience Required

Minimum Firm Experience
  • At least 15 years of experience in water supply and sanitation engineering
  • At least 10 years in detailed design and construction supervision of WSS infrastructure
  • Demonstrated experience with urban water treatment, transmission, storage, distribution, SCADA, wastewater, sewerage, pumping stations, and fecal sludge treatment
  • At least two comparable assignments financed by multilateral development partners within the last seven years
  • Demonstrated experience in Africa and with international conditions of contract including FIDIC or equivalent
  • Established QA, environmental and social, OHS, and design management systems
Contract & Payment Arrangements
  • Contract type: Lump-sum for feasibility, design and procurement support; time-based for construction supervision and DLP support
  • Payment: Linked to approved deliverables (lump-sum) and verified personnel inputs and reimbursables (time-based)
  • Duration: 46.5 months with overlapping phases as approved in the work program
  • Proposals: Technical and financial proposals shall address all tasks, personnel, reimbursables, and deliverables required by this TOR
  • Selection method: Quality and Cost Based Selection (QCBS)

Indicative Key Expert Positions (19 Roles)

# Position Primary Role
1Team Leader / Senior Water and Sanitation EngineerOverall leadership; design integration; contract administration; client coordination
2Deputy Team Leader / Resident EngineerDay-to-day coordination and supervision; site leadership
3Water Supply / Hydraulic EngineerWater demand, modelling, treatment, transmission, storage, distribution, and connections
4Wastewater and Fecal Sludge Process EngineerFSTP/WWTP process assessment, technology selection, detailed design, commissioning
5Sewerage and Drainage EngineerSewer assessment, hydraulic design, rehabilitation, pumping, outfall interfaces
6Electro-Mechanical EngineerPumps, treatment equipment, power, controls, standby systems, testing
7SCADA / Instrumentation SpecialistAutomation architecture, telemetry, instrumentation, functional specifications, commissioning
8Structural EngineerReservoirs, treatment structures, buildings, stations, and rehabilitation
9Geotechnical EngineerInvestigations, foundations, earthworks, pipeline geotechnics, constructability
10Quantity Surveyor / Cost and Contract SpecialistBOQs, cost estimates, payment certification, variations, claims, final accounts
11Quality Assurance / Materials EngineerQA/QC systems, materials, laboratory and field testing, source inspection
12Environmental SpecialistE&S assessment, ESMP integration, monitoring, pollution prevention, reporting
13Social SpecialistStakeholder engagement, land and livelihood impacts, GRM, social monitoring
14OHS SpecialistWorker and community health and safety, contractor systems, incident prevention and monitoring
15Climate Resilience / Energy SpecialistClimate risk, resilience measures, energy efficiency, and GHG considerations
16Surveyor / GIS SpecialistTopographic and route surveys, setting-out, GIS database, asset mapping
17Socio-EconomistSurveys, demand, affordability, beneficiary and service-level analysis
18Financial / Economic AnalystLifecycle costing, economic and financial analysis, sensitivity assessment
19CAD/BIM Technicians and Site InspectorsDrawings, document control, daily inspections, records, measurements

Indicative Deliverable Schedule (20 Outputs)

# Deliverable Component Indicative Timing
1Draft Inception ReportAllMonth 1
2Final Inception ReportAllMonth 1.5
3Urban Water Feasibility StudyWaterMonth 3
4Urban Water Preliminary DesignWaterMonth 4
5Urban Water Detailed DesignWaterDraft Month 6; Final Month 6.5
6Urban Water E&S Instruments / UpdatesWaterMonth 7
7Urban Water Procurement PackageWaterMonth 7
8Urban Sanitation Feasibility StudySanitationMonth 5.5
9Urban Sanitation Preliminary DesignSanitationMonth 7.5
10Urban Sanitation Detailed DesignSanitationDraft Month 9.5; Final Month 10
11Urban Sanitation E&S Instruments / UpdatesSanitationMonth 10.5
12Urban Sanitation Procurement PackageSanitationMonth 10.5
13Procurement Support Report — WaterWaterBy Month 13 or upon completion
14Procurement Support Report — SanitationSanitationBy Month 16.5 or upon completion
15Monthly Progress SummaryApplicable phaseWithin 7 days after month-end
16Quarterly Progress ReportApplicable phaseWithin 7 days after quarter-end
17Construction Completion / Close-out ReportEach works contractWithin 2 months of substantial completion
18Quarterly DLP ReportEach works contractQuarterly during DLP
19Final Consultancy ReportAllOne month before service completion
20Final As-Built and Handover ReviewEach works contractBefore final completion

“The overall objective is to prepare technically sound, climate-resilient, environmentally and socially compliant, economically justified, and procurement-ready urban water and sanitation investments — and to support their implementation through procurement, construction supervision, commissioning, and the defects liability period.”

Download the Full Approved Terms of Reference (PDF) WASAP — Gambia Water and Sanitation Project  ·  P513113  ·  Official Use Only  ·  Republic of The Gambia / Ministry of Petroleum, Energy and Mines / NAWEC
⬇ Download TOR (PDF)